As discussed during standup yesterday, due to illness and other factors,
we're proposing to add three days of development time to Release 2.5. This
would push code close to EOD Wednesday, 6/20. The two days following would
be used for a documentation sprint and QA setup. We would shoot for full
regression testing and release to wrap up on Friday, July 6th.

Scope week for Release 2.6 would remain the week of June 18-22, due to
Patrick's vacation the following week, and design week for 2.6 would begin
on July 9th.

Please let me know if anyone has questions/concerns about this proposed
schedule change.

Best regards,
Megan